Clinton Electric coordinated with BGE to install new 800 amp 480 volt 3 phase service to a transformer on site in Abingdon, Harford County, Maryland. The parking lot in this premier shopping destination was already finished but required power be delivered 220′ from the source to the proposed charging station location. Clinton Electric bored under the existing asphalt to install two 4″ conduits for power delivery. Wired from CT cabinet to four CPE200 units and one CT4000 on concrete pads. This project included everything from designing the layout, coordinating with utilities, furnishing and installing the equipment and painting the lines green on the parking lot.